CLICK pic' for download
using for course Quantity Measurement as reference in Chap. 3 and Chap. 4
kredit to http://jurukurbahan.blogspot.com
Calculate the rate of 1m3 of concrete | |||||
Concrete Gade 40 (1kg cement : 1.16kg sand : 2.45kg agg) | |||||
Details: | |||||
Cement (density, 1350 kg/m3) | RM200.00/tonne | ||||
Sand (density 1550kg/m3) | RM60.00/tonne | ||||
Aggregate (density 1400kg/m3) | RM70.00/tonne | ||||
Labour contant for mixing | 2.75hrs/m3 | ||||
Labour constant for carry and pour | 1.75hrs/m3 | ||||
Labour constat for compaction | 0.75hrs/m3 | ||||
Labour's wage per day | RM24.00 | ||||
Wastage | 50% | ||||
Profit | 15% |